Site
Preparation Guidelines
Barns
or Run-in Sheds with Overhang
or Modular Barns
Recommend concrete
pillars - 18" in diameter, 3’ – 4’ deep (below
the frost line) and 3” – 4” above ground level. This
will prevent the building from "settling" unevenly due to ground
freezing/thawing cycles which can change the ground level over time. We
recommend these footers be placed at the building corners and every 12'
under the foundation, around the building's perimeter. We will give you
a footer diagram showing exact measurements and placement for your specific
barn.
- After the building is delivered, the area around
the barn and under the overhang can then be back filled with stone
dust to pillar height. If you desire cement in the center aisle or
under the overhang, that can be poured after the barn is delivered
as well.
For safety reasons, some townships require that the building
be anchored. This is sometimes referred to as a "hurricane kit."
Be sure to check with your municipal agency regarding this requirement.
Anchoring your building will help stabilize it against side-to-side shifting
or vertical lifting in the event of high winds.
- The easiest way to anchor a barn set on cement pillars
is to get a 2' piece of 1" wide steel strapping/banding for each
pillar. When pouring the pillar, insert 1' of the strapping into the
wet cement allowing 1' to stick out the top. This strap can then be
folded over and the barn set on top of it. To avoid any interference
with the building's steel re-enforced corners, we recommend that the
steel strapping be folded into the barn and bolted on to the 6x6 timber
foundation, from the inside, after the barn is set down.
- Another option would be to use a ¼" steel
hurricane bracket. This bracket would be bolted to the concrete footer
with concrete screws and then lag bolted to the 6x6 that makes up
the base of the building.